Structural Alterations
£2.0 million
Structural alterations, cut & carve, to existing building on John Adam St, including temporary propping, extensive demolition, new steelwork & construction of new concrete structure
500T rubble removed / 40T Structural Steelwork /450m3 concrete installed
The works comprise of the demolition of elements of the existing structure, including the remodelling of the existing lift shaft including steelwork / concrete alterations, the infilling of an existing atriums and the construction of service risers / loading bay areas within the existing building