Structural Steelwork
£3.2 million
Installation of steel structure as temporary platform base to atrium, demolition & removal of slabs, construction of blockwork & RC concrete walls, installation of structural steelwork, installation of sprung concrete floor to gymnasium / running track area.
The works
comprised of the demolition of existing structure within an existing building,
including the incorporation of steelwork / temporary propping and RC concrete
structure. The installation of a specialist sprung concrete floor slab,
blockwork and general structural adaptations.